The Vision Pratumnak Hill Pattaya construction update 25 February 2014

The Vision - Construction update as 25 February 2014
Structure work 96.820%
Architecture and Finishing work 28.349%
Electric System works 39.536%
Sanitary System Works 49.859%

Construction expected to be completed Q4 2014


Photograph shows the lift core and column on 23rd floor